Windham Intermodal Transportation Center / Parking Garage

Client

Services

Size

Value

PROJECT Details

In January 2020, O&G was awarded the contract to construct the 107,000 GSF Windham Intermodal Transportation Center in downtown Willimantic, CT. Despite challenging weather conditions during the winter of 2020-2021, O&G self-performed all the site work and concrete foundation placement in preparation for the erection of the 343 prefabricated components of the structure in the Spring of 2021. Working closely with the Windham Town Engineer, Walker Consultants out of Boston, Blakeslee Prestress from Branford, along with a team of trade partners, O&G successfully completed the project on schedule in October 2021 and close to $1,000,000 under budget.

Architect / Engineer